Emerald Park Access & Railroad Crossing
For the Week of November 6-10, 2017
generated 11/03/2017

HIGHLIGHTS, CLOSURES & DELAYS

  • FINAL Weekly Construction Update As City Projects Wrap Up for Season
  • Emerald Park Phase I Cleaning Up For Winter Work Moratorium

Construction activity will still occur through open construction zones the week of November 6. Crews will be wrapping Phase I with punch list work and cleaning up the site for the winter work moratorium. Access to all businesses will kept open throughout construction.  
 
DSC01671a_thumb.jpg 

During the project, United Companies and the City of Steamboat Springs will recycle 877 tons of existing asphalt and 84 tons of existing concrete while incorporating 352 tons of new asphalt from recycled asphalt materials. A project hotline (970-871-8243) and email () has been set up for updates, notifications and information.


Emerald Park Access-RR Crossing_thumb.png


Construction Updates
11.03.2017 Construction Update
10.27.2017 Construction Update
10.20.2017 Construction Update
10.13.2017 Construction Update
10.6.2017 Construction Update
9.22.2017 Construction Update
9.15.2017 Construction Update
9.8.2017 Construction Update
9.1.2017 Construction Update
8.25.2017 Construction Update
8.18.2017 Construction Update
8.11.2017 Construction Update
8.4.2017 Construction Update